Tonne ferrous metals recycled

312

Tonne non-ferrous metals recycled

6062

Tonne concrete & bricks recycled

Project Summary

Summary Chemical Plant Demolition
Client DOW Chemicals
Schedule 27 Weeks 
Location Altona, Victoria, AUSTRALIA
Outline Demolition of various Structures within the Altona Processing Facility, including buildings, superstructures, tanks, pipes and pipe racks.
Outcome Throughout the project, Ausdecom methodically planned strategies and applied expertise, including engineered collapses of units and use of cranes, to successfully complete the Scope.

Scope of Work Completed

The Dow Chemical Demolition Project comprised the demolition of buildings, tanks, pipes and pipe racks (Stage 1) and the demolition of the POD processing Area (Stage 2), which mainly contained tanks, towers, reactors, process vessels and superstructures.

Throughout the project, Ausdecom methodically planned strategies and applied expertise, including engineered collapses of units and use of cranes, to successfully complete the Scope.

Hazardous material removal was a significantly large campaign in both stages. 202.48 T of Hazardous material were removed, transported and disposed off site.

In continuous consultation with the Dow Chemical representatives, Ausdecom honored client requirements, and thoroughly reviewed the unique project risks, including but not limited to:
• Working adjacent to live infrastructure,
• Managing residual chemical and refractory material,
• Managing unexpected asbestos finds,
• Site Stakeholders and simultaneous operations

http://Ausdecom%20Demolition%20Chemical%20Plant%20Project
http://Ausdecom%20Chemical%20Plant%20Demolition%20Completion
http://Ausdecom%20Chemical%20Plant%20Demolition%20Big%20Blue%20Excavator

Works Included:

  • Demolition of various Structures within the Altona Processing Facility, including buildings, superstructures, tanks, pipes and pipe racks
  • Friable and Non-Friable Hazardous Material Removal