10300

Tonne concrete recycled

500

metres effluent pipe removed

8

months completion

Project Summary

Summary Site Demolition & Removal
Client BASF Australia Pty Ltd
Schedule 8 months
Location Altona, VIC, Australia
Outline Demolition of buildings and removal of hardstand.
Outcome Following removal of all scope items, Ausdecom removed all waste materials including protruding reinforcement and/or trip hazards and handed back the site to BASF ready for its future use.

Scope of Work Completed

Demolition of buildings and removal of hardstand.
The manufacturing plant in Altona was stripped of all possible items a separation made and the building collapsed in a controlled manner and then processed at ground level.
Following removal of all scope items, Ausdecom removed all waste materials including protruding reinforcement and/or trip hazards and handed back the site to BASF ready for its future use.

http://Ausdecom%20BASF%20Altona%20Demolition%20and%20Removal
http://Ausdecom%20Site%20Demolition%20and%20Removal%20BASF%20Altona
http://Ausdecom%20BASF%20Altona%20Site%20Demolition%20and%20Removal

Works Included:

  • Internal strip out of warehouse and cold storage facility including mezzanine offices
  • Removal of asbestos wall and roof sheets
  • Demolition of cold store facility
  • Mechanical demolition of warehouse structure consisting of brick and concrete tilt panel walls
  • Mechanical demolition of steel wall columns, purlins and roof trusses
  • Demolition of effluent plant and pipeline
  • Removal of over 500m effluent pipeline from live pipe rack within neighboring DOW Chemical plant
  • Removal and recycling of over 10,300t of concrete slab and footing