605

Tonne Concrete & Asphalt Recycled

120

Tonne Ferrous & Non-ferrous Metal Recycled

2400

Tonne Cat B & C PFAS impacted soil remediated

Project Summary

Summary Tank Demolition & Site Remediation
Client VIVA Energy Australia
Schedule 10 weeks
Location Newport, VIC, Australia
Outline Demolition works comprised of the careful dismantling of the former T37 and T38 diesel storage tanks and all associated infrastructure within the works area.
Outcome
  • 605 T – Concrete and asphalt recycled
  • 120 T – Ferrous and non-ferrous metal recycled
  • 240 T – Category B PFAS Impacted soil remediated
  • 290 T – Category B PFAS impacted soil with Asbestos abated
  • 1870 T – Category C PFAS Impacted soil remediated

Scope of Work Completed

Demolition works comprised of the careful dismantling of the former T37 and T38 diesel storage tanks and all associated infrastructure within the works area. These works also involved the careful management of PFAS impacted concrete from the former Fire Training Facility present in the works area.
Ausdecom ensured numerous barriers and safety regulations were in place throughout the removal works which were closely monitored by the onsite supervision and management team.
As part of the Scope of works, Ausdecom were also required to remediate approximately 2,400 tonnes of Category B and Category C PFAS impacted soil in conjunction with the ongoing demolition works. Ausdecom supported the team of onsite Hygienists in the sampling and validation process of each soil stockpile through a means of test pitting, relocation, and inspection procedures.
Due to the presence of friable and non-friable asbestos identified within the soil stockpiles, a large portion of the soil had to be excavated, inspected, and abated prior to transport offsite to licensed treatment and disposal facilities. All soil and concrete stockpiles were carefully segregated into the different waste streams to ensure compliance with EPA classification, transport, and offsite disposal legislation.
Given the nature of soil contamination and works with asbestos, Ausdecom were required to, and successfully implemented careful stakeholder management ensuring that interactions with third party contractors as well as the general public were coordinated without incident.
Throughout the lifecycle of the project, Ausdecom worked closely with VIVA Energy to ensure all site safety regulations, and permits were adhered to by all personnel, thus fostering a trusting relationship with the client and allowing the project to progress safely and smoothly.
All works were undertaken whilst maintaining a good relationship with other onsite contractors and without the need to halt operations occurring within the immediate vicinity of the works area.

http://Soil%20Abatement
http://Soil%20Remediation
http://Tank%20Demolition

Works Included:

  • Abatement of asbestos contaminated soil from soil stockpiles.
  • Sampling, categorization support and site remediation of PFAS impacted soils.
  • Careful demolition and process PFAS impacted fire training area concrete slabs and foundations.
  • Dismantling and removal of all nominated structures within works area. Structures included: large diesel storage tanks, drainage pits, channel drains, hydrant lines, bluestone platforms, light poles, overhead pipework and pipe racks, monitoring wells, asphalt pavement and storage shed.

 

 

WASTE STREAM MANAGEMENT INCLUDING RECYCLED MATERIALS:
  • 605 T – Concrete and asphalt
  • 120 T – Ferrous and non-ferrous metal
  • 240 T – Category B PFAS Impacted soil
  • 290 T – Category B PFAS impacted soil with Asbestos
  • 1870 T – Category C PFAS Impacted soil